moving toilet 5", so at 1/4" per foot, soil pipe now 1-1/4" higher than at original connection point, so.....vertical rise for the flange long sweep elbow brings flange almost 1" above existing slab...I need that flange in the pic, I believe to adjust it to be horizontal
seeing some posts where ok to use standard or 4x3 elbow which does not have as much vertical rise, I thought code req'd the long sweep?
somehow raise floor 1", at least in and around toilet? that would be a royal pain and honky to boot!!
any suggestions
seeing some posts where ok to use standard or 4x3 elbow which does not have as much vertical rise, I thought code req'd the long sweep?
somehow raise floor 1", at least in and around toilet? that would be a royal pain and honky to boot!!
any suggestions