Everything in red is existing. I plan to wet vent from the new 3” Vent. That wet vent would end at the toilet prior to the existing 1.5” vent, which is connected to the drain via a 3x3x3 wye and hub, which is inline with the proposed new plumbing upstream and existing plumbing downstream. Would it be to correct to increase the 1.5” Vent size and start a new wet vent for the remaining fixtures downstream? So it would be essentially 2 inline wet vents. IPC code here
I hope I’m interpreting this correctly. Option 3 would be ideal. By venting the wc into the 1.5”(changed to 2”)solves my problem with the wc not being the last fixture on the wet vent?
Hey Frodo, this is all that currently exists in that section. The vent is inline with the drain.
Is this how the toilet in the new location should tie in?